Contract tracking

Which contract is really behind?

  • DAX
  • Power BI
  • Excel
  • EVM

The problem

Percent spent alone cannot compare contracts of different value and duration.

Measures

Planned Value =SUMX (    Contracts,    Contracts[Value] * DIVIDE (        MIN ( MAX ( 'Date'[Date] ), Contracts[End] ) - Contracts[Start],        Contracts[End] - Contracts[Start]    ))Earned Value  = SUM ( Claims[WorkDoneValue] )Actual Cost   = SUM ( Claims[PaidValue] )SPI = DIVIDE ( [Earned Value], [Planned Value] )CPI = DIVIDE ( [Earned Value], [Actual Cost] )Elapsed % = DIVIDE ( [Planned Value], SUM ( Contracts[Value] ) )Spent %   = DIVIDE ( [Actual Cost], SUM ( Contracts[Value] ) )Status =VAR Gap = [Elapsed %] - [Spent %]RETURN    SWITCH (        TRUE (),        ISBLANK ( Gap ), BLANK (),        Gap < 0.10, "Excellent",        Gap < 0.15, "Good",        Gap < 0.20, "Weak",        "At risk"    )

Classification rule

Gap = % time elapsed − % spent

Gap

+18

  1. Excellent
  2. Good
  3. Weak
  4. At risk

Illustrative example

ContractTime elapsedSpentSPICPIStatus
Contract A62%58%0.961.02Excellent
Contract B71%54%0.820.97Weak
Contract C48%25%0.610.92At risk

Selecting the latest claim

// "Latest row wins" is only safe if the latest row is complete.Latest Claim =VAR LastComplete =    CALCULATE (        MAX ( Claims[ClaimNo] ),        NOT ISBLANK ( Claims[Contractor] ),        NOT ISBLANK ( Claims[Scope] ),        ALLEXCEPT ( Claims, Claims[ContractNo] )    )RETURN    CALCULATE ( SUM ( Claims[WorkDoneValue] ), Claims[ClaimNo] = LastComplete )

Result

  • One verifiable standard for every contract.
  • The same status in the board, report and deck.

Figures and examples are illustrative.